These documents on Project Management (WBS 1.1) and sub-topics are available:
Showing documents with topic Project Management (WBS 1.1) on the most recent version. See documents with Project Management on any version.

LBNE-doc-# Title Author(s) Topic(s) Last Updated
34-v6 Report on the Depth Requirements for a Massive Detector at Homestake Milind Diwan Physics
Conventional Facilities
DUSEL
Requirements
02 Sep 2015
3383-v59 DUNE Far Detector 1 Parameters spreadsheet Russ Rucinski CD-1-R DOE Review
Requirements
Liquid Argon Detector
BOE-LAr
CD-1-R Director's Review
28 Aug 2015
6681-v1 LBNE CD-1 Approve Alternative Selection and Cost Range Author Non-LBNE CD-1-R DOE Review
Project Management
CD-1-R Director's Review
28 Aug 2015
11104-v2 LBNF Cryostat Independent Design Review Committee Report Author Non-LBNE Project
LAr-Cryogenics & Purification
Reviews-Internal
11 Jun 2015
11105-v2 LBNF Cryo System Independent Design Review Committee Report Author Non-LBNE Project
LAr-Cryogenics & Purification
Reviews-Internal
11 Jun 2015
11013-v1 Location of Building 327 James Strait Project Management
LBNE Collaboration
22 May 2015
10990-v1 LBNF Project Organization Chart Elaine McCluskey Project Management
20 May 2015
10797-v4 LBNF Cryostat Independent Design Review Charge James Strait LAr-Cryogenics & Purification
Project Management
20 May 2015
8920-v6 VE-FD-027 Place APA or short drift cell nearest wall Russ Rucinski et al. LAr-TPC & Cold Elec & HV
LAr-Cryogenics & Purification
Value Engineering
Liquid Argon Detector
14 May 2015
9588-v2 Overview of 35ton Phase 2 Detector Bo Yu Reviews-Internal
LBNE 35 ton prototype
07 May 2015
10006-v3 Far Detector Development Plan James A. Stewart Value Engineering
Liquid Argon Detector
R&D Coordination
15 Apr 2015
8741-v2 Far detector requirements documents Kate Scholberg Supernova Neutrinos
Requirements
15 Apr 2015
4892-v12 CDR Volume 4: The Liquid Argon Detector at the Far Site Mark Adamowski et al. DOE CD-1 Review
CDR
Reviews-Internal
Liquid Argon Detector
22 Aug 2014
4382-v3 Alternatives Analysis Elaine McCluskey Project Management
08 Feb 2014
6756-v1 CR0007 Temperature profiler proposal for the 35 ton Cryostat Hans Jostlein LAr-Cryogenics & Purification
LBNE 35 ton prototype
Change Control
28 Feb 2013
3472-v18 Requirements documentation Anne Heavey Requirements
20 May 2013
3056-v8 Physics Research Goals of the LBNE Project James Strait Project
Physics
Project Management
Requirements
LBNE Collaboration
15 Jan 2013
4724-v12 CDR Volume 3: Detectors at the Near Site Larry Bartoszek et al. DOE CD-1 Review
Near Detector Systems
CDR
Reviews-Internal
05 Nov 2012
2248-v27 LBNE Organization Chart Mike Dinnon Organization
27 Nov 2011
5968-v24 LBNE Reconfiguration Engineering/Cost Working Group Final Report Jeff Appel et al. Near Detector Systems
Project
Project Management
Conventional Facilities
Beamline
Liquid Argon Detector
09 Aug 2012
2910-v5 LAr mini review: WBS 1.5.4 DAQ Jon Urheim Project
Reviews-Internal
Liquid Argon Detector
20 Jan 2012
3019-v4 LAr mini review DAQ breakout: DAQ System Design Concept Jon Urheim LAr-DAQ
Reviews-Internal
20 Jan 2012
4352-v1 Science Ca[ability Review Charge Robert Svoboda Reviews-Internal
Executive Board
05 Oct 2011
4233-v1 Job description: LBNE Project Scientist James Strait Project Management
01 Sep 2011
3635-v1 FY2012 HEP President's Budget Request Author Non-LBNE Budget
19 Apr 2011
3501-v1 Charge to the Marx Committee Author Non-LBNE DUSEL
Reviews-DOE
LBNE Collaboration
28 Mar 2011
3307-v1 DOORS: Report on initial investigations Anne Heavey Requirements
26 Jan 2011
2473-v2 Report from Director's Mini-Review, 15-16 July 2010 Committee Director's Review Reviews-Directors
09 Sep 2010
2448-v1 DOE NEPA Determination Author Non-LBNE Project Management
12 Jul 2010

Number of documents found: 29

DocDB Home ]  [ Search ] [ Last 20 Days ] [ List Authors ] [ List Events ] [ List Topics ] [ Fermilab Documentation Templates ]


DocDB Version 8.8.9, contact LBNE Document Database Administrators
Execution time: 45 wallclock secs ( 5.74 usr + 1.38 sys = 7.12 CPU)